Sterling Water Treatment Plant

< BACK TO ALL PORTFOLIOS

Project Overview

LOCATION:

Sterling, CO

CLIENT:

City of Sterling

CATEGORY:

Water

CONTRACT MODEL:

Design/Bid/Build

The Full Story

Construction of a new 10MGD reverse osmosis water treatment plant.  Main treatment plant site includes 20,500 sq. ft. chemical building and includes a process and administration area.  An additional 4,000 sq. ft. chemical building sits adjacent to the main building and provides chemical pumps and storage.  Plant includes two cast in place water storage tanks, chemical feed systems, three RO trains, concentrate pumping system and process and yard piping.  Concentrate water from the RO skids is disposed of in two deep wells.  A deep well pump station was constructed to pump concentrate water into one of the deep wells.  This pump station includes two 300 HP, 550PSI multi stage pumps and associated stainless high pressure 900# flanged piping.

By The Numbers

Total contract amount

$14,845,400

Percent with own forces

60%

Year Completed

2014