South Fort Collins Sanitation District Headworks Repurposing

< BACK TO ALL PORTFOLIOS

Project Overview

LOCATION:

Fort Collins, CO

CLIENT:

South Fort Collins Sanitation District

CATEGORY:

Wastewater

CONTRACT MODEL:

Design/Bid/Build

The Full Story

Repurposing of existing Headworks building which includes prepping and painting all interior wall and floor surfaces, replacement of all manway doors, demolition and removal of all abandoned equipment, electrical, HVAC, process piping and plumbing.  Work also includes filling voids and accesses with concrete and patching all pipe and electrical penetrations.

By The Numbers

Total contract amount

$157,074

Percent with own forces

37%

Year Completed

2017