Lakewood, CO
Consolidated Mutual Water Company
Water
CMAR
This three-phase project included construction of a post-tension water tank which utilized self-consolidating concrete and received an American Concrete Institute Award of Excellence. Additional phases included construction of a treatment facility consisting of submerged microfiltration units, concrete wet-well, chemical feed systems and pre-treatment basins, a pre-treatment building with chemical feed equipment, piping and storage tanks, pre-treatment equipment and structures for sedimentation, flocculation, and PAC tanks
Total contract amount
$19,481,260
Percent with own forces
58%
Year Completed
2009