Demo existing pumps and PVDF piping, core six-inch hole in concrete tank wall and install new PVC piping with double link seal through the wall. Install new pumps, PVC, and PVDF piping for new pump configuration.

By The Numbers

Total Contract Amount

$19,680

Percent with Own Forces

100%

Year Completed

2017