Estes Park, CO
Estes Park Sanitation District
Wastewater
Design/Bid/Build
Construction of a 55 foot by 60 foot headworks building, including associated site and equipment improvements, a new dissolved air flotation (DAF) system, ultraviolet (UV) treatment, chemical feed, pump systems, fine screen, and grit removal equipment. The project also included effluent basin and lift station improvements with a complete electrical gear retrofit of the existing treatment plant.
Total Contract Amount
$3,535,560
Percent with Own Forces
60%
Year Completed
2016