Dillon, CO
Dillon Valley Metropolitan District
Water
CMAR
Constructibility and cost estimating during design phase. Demolition of existing filters, piping, valves, and tanks. Stock frame building addition to match existing. Installation of micro-filtration equipment, associated piping and valves, electrical , instrumentation and controls. Construction of chemical doc, equipment and tubing. Upgrades to existing intake, lighting and HVAC, all while maintaining plant operations.
Total contract amount
$2,873,473
Percent with own forces
80%
Year Completed
2014